Required equipment:
The sink cone is placed on the worktop and filled with concrete with the help of a dowel bar. The cone is slowly lifted from the worktop. The sinking of the concrete is determined by reading how much it has sunk down.
The sink cone is placed on the fall table and filled with concrete. Wooden rammers are used to level out the concrete in the cone.
The spread of the concrete is determined by lifting and releasing the table several times, so that the concrete flows out. Distribution is measured in mm.
Sink propagation Self-compacting concrete (SKB)
The sink cone is placed on the worktop and filled with concrete with the help of a dowel bar. The cone is slowly lifted from the worktop. The extent of the concrete is determined by reading the diagonal dimensions of the circle.
Used to measure the flow properties of fresh concrete.
Goal:
900x900mm
Goal:
700x700mm
Concrete trays: Square – suitable for filling test moulds for cubes
Concrete bucket: Round – suitable for filling sink cones and air pore buckets
Rund betongskuffe